Hi
When entering a workload in Sizer, there is an option to select the existing CPU.
For example, let’s assume that we are planning to deploy 100 VMs, each with 4 vCores and 8 GB of memory.

If I select “Yes, but I don’t know the current processor” and then choose Default, the estimated CPU utilization is approximately 75% when configured with a 3-node cluster, each node having 2 CPUs with 32 cores.
However, if I edit the workload and select “Yes, but I don’t know the current processor”, the estimated CPU utilization increases to around 110%.
In other words, I am not sure which criteria I should use when performing sizing.
Why does the estimated utilization differ so significantly even though the workload itself is the same?
Is there any detailed guidance available for this? It may be that I have not been able to find it, so I would appreciate your assistance.