Question

"download and deploy prism central" neverending task


Badge +5
I tried to install Prism Central, the task named "download and deploy prism central" is now 100% since three days and i cannot stop it through PRISM interface.

I have seen that ncli has a "task" command, but looks like not useful. I have been trying to find the task with "progress-monitor" command, but it shows nothing related to prism central.

How can I stop it? Or at least clean the task to proceed with a new installation?

2 replies

Userlevel 4
Badge +19
@iancafdfds You can find the task under "acli".
If you still have the issue, can you contact nutanix support with a case and we will help to clear the task.
Userlevel 7
Badge +35
Hi @iancafdfds

Did the reply from @sandeepmp help? If yes, consider clicking the 'Best Answer' link - that will help others on the community find answer to the same question more quickly. Thanks

Reply