Question

HX1320 Certified Nodes - installation of 2-nodes

  • 18 September 2018
  • 0 replies
  • 237 views

Hi everyone,

My customer tried to install HX1320 Certified Nodes with 2 nodes.
These are combination of SW tried install.
==============
#1
Foundation : 4.0.5
AOS : 5.6.2
AHV : 20160925.91

#2
Foundation : 4.0.5
AOS : 5.6.2
AHV : 20170830.94

#3
Foundation : 4.0.5
AOS : 5.6.2
AHV : 20170830.124

#4
Foundation : 4.1.2
AOS : 5.8.2
AHV : 20170830.166
==============
But these all trying was failed.
Always failed situation was same that one node completed installation and the other node failed installation at progress of 39%. Also failed messages was same all the times; "because dependencies not met".
And there is an one unusual thing. Network switch is a 1G L2 switch, I don't know about detail spec of switch.
My question is, is there any specified condition of switch to install Certified Nodes?

0 replies

Be the first to reply!

Reply